Owner-Appointed Contractors
General Terms & Working Rules
We can work alongside owner-appointed contractors as long as boundaries are clear. These terms are to protect the renovation schedule, completed finishes, and reduce misunderstandings.
1) Communication & Coordination Method
The owner will create a group chat including the By Design and the owner’s contractor.
What we will do
- We will inform in the group chat when the contractor may enter / which stage is suitable, based on site readiness and renovation sequence.
What we will not do
- We do not chase, schedule, or manage the contractor’s attendance, manpower, deliveries, or warranty follow-ups.
Communication rule
- English text only for instructions and confirmations
- No voice notes
- If the contractor cannot communicate in English, the owner must translate and confirm in English text
2) Scope & Responsibility Boundary
Owner-appointed contractors are not under By Design’s supervision.
- The owner is responsible for the contractor’s workmanship, safety, timeline, tools, and warranty
- By Design is responsible only for By Design’s workmanship
- Any disputes relating to third-party works are between owner and owner’s contractor
3) Site Access Windows & Sequencing
Third-party works must be:
- Declared early (before our schedule is locked)
- Performed only within the approved access windows
- Coordinated so they do not disrupt critical renovation sequence
If third-party works cause delays, return trips, or rework, any additional manpower/return visits may be chargeable as a Variation Order (VO).
4) Protection, Cleanliness & Moving Items
Owner’s contractor must:
- Protect floors, walls, carpentry, glass, sanitaryware, and completed finishes
- Keep the area tidy and clear debris after works
- Follow building management rules (timings, lift booking, disposal)
Important note: When contractors move ladders, glass panels, tools, vinyl planks, aircon units, etc., it is common to accidentally hit:
- doors / door frames
- walls, corners, skirtings
- cabinet edges and laminates
Any damage from third-party delivery/handling/installation is under owner/owner-contractor responsibility and should not be treated as renovation defects.
5) Materials, Tools & Storage (Owner Contractor)
- Owner contractors should not leave tools/materials in the unit unless the owner manages it directly.
- By Design does not receive, store, safeguard, or track third-party tools/materials.
- Loss/missing items or damaged packaging are under owner/owner-contractor responsibility.
6) Damage Responsibility (Documentation Is Owner/Contractor’s Duty)
To avoid misunderstandings when multiple parties enter the unit:
Before starting work (mandatory):
- Contractor/owner to take clear photos/videos of the work area and nearby finished surfaces
- Post in the group chat: “Before work – [date/time] – [area]”
After finishing work (mandatory):
- Contractor/owner to take clear photos/videos of the same area
- Post in the group chat: “After work – [date/time] – [area]”
If documentation is not provided:
- Any damage or “defect” claims in that affected area will be handled based on available evidence and scope; where responsibility cannot be reasonably verified, it will be treated as under owner/owner-contractor scope.
7) Handover & “Defects” Boundary
Before handover, owners may still invite third-party contractors into the unit. Please note:
- Damage caused by third-party works is not considered By Design defects
- If new marks/dents/scratches appear after a third-party visit, rectification (if requested from By Design) will be a chargeable VO
This keeps defect checking fair and prevents “last-minute” defects being pushed to the renovation team.
8) Recommended Timing (Best Practice)
To minimise overlap risk, owner-appointed contractors should be planned either:
- before renovation starts, or
- after handover, where suitable
Aircon (Special Note: Usually 2 Trips)
Aircon works commonly involve:
- First trip: trunking / piping / drainage route
- Second trip: install units + final commissioning (usually near the end)
Because the second trip is close to completion, strict protection and documentation is important. Any rework caused by aircon routing changes, patching, repainting, touch-ups, or condensate issues is under owner/owner-contractor scope unless explicitly included in our quotation.
9) Reporting Timing (So Issues Don’t Drag On)
If the owner notices an issue believed to be linked to third-party works, please report in the group chat:
- within 24 hours of the contractor’s visit (where practical), and
- with clear photos and location
Late reporting may limit verification and may be treated as a general rectification request (chargeable if outside our scope).
10) Optional: Third-Party Coordination Support
If the owner wants By Design to do more than basic schedule coordination (e.g., chase contractor, align schedule, oversee interfaces, check workmanship), this can be provided as a paid add-on service, subject to availability.